Construction Update 06-30-2016

The backfilling of the abutments and wing wall has been completed. The erection of the bridge structural steel is set to begin the week of July 11th. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house was delivered and erected this week with internal mechanical work ongoing and pump station electrical work to follow.

Work Zone Cameras can be viewed under the Photos Tab on the website.

The backfilling of the abutments and wing wall has started in conjunction with the removal of the temporary sheeting around the abutments. The erection of the bridge structural steel is set to begin the week of July 11th. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house was delivered and erected this week with internal mechanical work ongoing and pump station electrical work to follow.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Backfilling of the abutments will start this week. Once this is complete most of the sheeting around the abutments can be removed and the structural steel set. This is anticipated to begin within the next two weeks. The storm sewer behind the west retaining wall has been completed. The contractor has begun backfilling in front of the west retaining wall. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house is scheduled to be delivered Friday with its assembly to follow.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 06-08-2016

With the completion of the Stage 1 north and south abutments, the next step will be to backfill each abutment and remove the sheeting. Once this is completed the structural steel will be erected. This is anticipated to begin within the next two to three weeks. Installation of the storm sewer behind the west retaining wall has begun. Meanwhile, preparations are being made to begin driving the temporary sheet piling for the retaining wall east of the tracks. The precast pump station house is scheduled to be delivered mid-June.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Construction Update 06-01-2016

The Stage 1 north abutment, south abutment, and west wing wall have been completed. The last panel of the west retaining wall has been completed. The back of the south and north abutment as well as the west retaining wall continue to be backfilled with its drainage system being installed concurrently. As the retaining wall is backfilled the temporary sheet pile is being removed. The structural steel is tentatively scheduled to be set the week of June 13th. The precast pump station house is scheduled to be delivered mid-June.

Work Zone Cameras can be viewed under the Photos Tab on the website.

Work Zone Cameras can be viewed under the Photos Tab on the website.