Construction Update 9-9-2015

Work on the roadway runaround continues. The contractor continues to pave the roadway runaround. This operation has been slightly delayed due to the recent rains. The runaround cannot be completed until the railroad completes the installation of the crossing signals. The contractor continues to form the intermediate slab for the Pump Station with a pour scheduled tomorrow. Once this is complete and cured construction of the walls will continue. Other ongoing operations include grading for the railroad shoofly.