Construction Update 8-26-2015

Work on the roadway runaround continues. The contractor is scheduled to pave the asphalt surface of the roadway runaround west of the tracks at the end of this week. The installation of the asphalt surface of the runaround east of the tracks is contingent on the railroad installing the track crossing material. After that, the railroad needs to install the crossing signals and the roadway runaround will be complete. The lower walls of the pump station have been installed. The contractor will form and pour the intermediate slab next week. The detention basin at the northeast section of the project is near completion with the topsoil being added yesterday. Other ongoing operations include grading for the railroad shoofly and the restoration of the bike path south of Washington Street.

Work Zone Cameras can be viewed under the Photos Tab on the website.