Construction Update 05-24-2016

The stage one north abutment, south abutment, and west wing wall have been completed. The last of the west retaining wall was completed today. The back of the south abutment as well as the west retaining wall continue to be backfilled with its drainage system being installed concurrently. As the wall is backfilled the temporary sheet pile is being removed. The structural steel is tentatively scheduled to be set at the beginning of next month. The precast pump station house is scheduled to be delivered at the end of this month. The basins along Haryan Way and along Lake Street north of Washington Street have been graded and seeded with erosion control blanket.

Work Zone Cameras can be viewed under the Photos Tab on the website.